蘑菇视频DT/2014/038, Hassanin
In the present case, the parties reached an agreement through mediation after the application was filed and the Tribunal will reject the application as being nonreceivable.
In the present case, the parties reached an agreement through mediation after the application was filed and the Tribunal will reject the application as being nonreceivable.
Upon review, the Tribunal concluded that the Applicant did not commit the misconduct of providing false information in his annual leave report. The Respondent correctly established the facts for the remaining charges of the misconduct. However, the Respondent did not fully take into account all the mitigating circumstances when determining the appropriate disciplinary sanction. The Tribunal found the disciplinary measure disproportionate to the misconduct and modified it. The contested decision is rescinded. The disciplinary measure of separation from service with compensation in lieu of...
The 蘑菇视频DT found that OHRM’s decision not to consider (endorse) her for a temporary P-3 post in DM (Umoja) and to deny her conversion from the FS-6 level to the P-3 level was valid and lawful. The decision not to consider the applicant eligible for a temporary P-3 post was correct since she only fulfilled one of the mandatory and cumulative conditions – five years of professional experience – in November 2011. The Organization properly determined that the Applicant could not be converted from the FS-6 level to the P-3 level because there was no contractual relationship between the Applicant and...
The Tribunal finds that the pertinent facts and the legal issues in the present cases are on all fours as those of the ICTY cases. As both parties have accepted the ratio decidendi of the decisions by the 蘑菇视频AT in the ICTY cases, the Tribunal adopts the Appeals Tribunal’s findings in Malmstr?m 2013-蘑菇视频AT-357 and remands the 蘑菇视频AKRT conversion exercise to the ASG/OHRM for retroactive consideration of the suitability of each applicant within 90 days of the date of publication of this judgment in accordance with the guidelines set out by the Appeals Tribunal in the matter of Malmstr?m. Taking into...
Neither DSS, OHRM, the CRB nor the ASG/OHRM conducted a reasoned analysis on how the date and the gravity of the disciplinary sanction impacted on the recommendation(s) and/or the decision not to grant him a permanent appointment. The Administration failed to apply its own Guidelines requiring that a mandatory review of the date and gravity of the disciplinary measure applied to the Applicant be conducted and that any resulting decision include a reasoned explanation thereto.
Decisions (a) and (b) are found not receivable and decision (c) is found to be unfounded. The Tribunal also finds that the Applicant’s request for management evaluation (MEU request) included a request for SPA which was not addressed by the Organization. The Applicant did not pursue the applicable procedure established in ST/AI/1998/9. In the absence of an actual administrative decision denying a request for reclassification, the application against the continuous refusal to reclassify his post from the P-4 level to the P-5 level is not receivable.The Applicant’s MEU request indicated that he...
The Tribunal found that the applications were receivable since the contested decisions produced direct legal consequences adversely affecting the Applicants’ terms and conditions of appointment. The Tribunal further found that the chosen period of retroactive application of one year was not only unlawful because it was based on a misconstruction and misapplication of staff rule 3.16 but it was manifestly unreasonable, irrational, and above all unjustifiably discriminatory. It did not amount to a proper exercise of administrative discretion and breached the fundamental principle of equal pay...
The Tribunal found that the USG/DESA complied with ST/SGB/2008/5 by closing the case and providing the Applicant with a summary of the Investigation Panel’s findings and conclusions. However the applicable mandatory time limits for assessing the complaint, appointing the panel and submitting the final investigation report were not respected. The Applicant is awarded a compensation in the total amount of USD2,300. The Tribunal found that there was no evidence that the Investigation Panel did not gather sufficient evidence or erred in reaching its findings and conclusions presented in the report...
The application was dismissed in its entirety. The Tribunal also found that the Applicant has manifestly abused the proceedings before it. The Applicant was ordered to pay costs in the sum of USD 2,000 for abuse of process. On receivability: The Tribunal found that the PDF version of the application attached to the email of 15 September 2012, also copied to OHRM and EO/OCHA, met the requirements of art. 8 of the Rules of Procedure of the Dispute Tribunal. It was moreover identical to the application filed through the e-filing portal on 15 October 2012. The Respondent’s contention that the...
The Tribunal found that the Administration violated the rights of the Applicant by not including the PAD cycle year 2009 when making the termination decision in July 2010. The Tribunal ordered the rescission of the contested decision and compensation for material damage equivalent to the loss of salary until her early retirement date on 1 May 2011. When terminating a contract for unsatisfactory service, the PAD reports to be taken into consideration must be the ones immediately preceding the non-renewal decision, so the PAD cycle years 2007, 2008, and 2009 for a termination decision made in...